Adani Energy Solutions Ltd has won a tariff-based competitive bidding project to evacuate 2,400 MW of power from Adani Power's upcoming thermal plant in Bihar. The project is expected to be completed by the fourth quarter of 2028 and will expand AESL's transmission capital expenditure pipeline to approximately ₹91,500 crore.

Adani Energy Solutions Ltd (AESL) has secured a transmission project to evacuate 2,400 MW of power from Adani Power’s upcoming ultra-supercritical thermal power plant at Pirpainti in Bihar. The project is projected to generate an annual tariff of roughly ₹500 crore once it is commissioned.

Awarded through the tariff-based competitive bidding (TBCB) route, the project is officially titled ‘Evacuation of Power from 3X800 MW STPP Pirpainti’. It will be implemented through a special purpose vehicle named Vikramshila Power Transmission Ltd. According to an official release, AESL expects to complete the implementation by the fourth quarter of 2028.

The infrastructure initiative is designed to strengthen Bihar’s transmission network and improve overall power supply reliability, alongside facilitating the evacuation of electricity generated by the 2,400 MW thermal power plant. The scope of work entails the construction of four gas-insulated substations (GIS) located at Jhanjharpur, Bethauli, and Begusarai, together with associated transformation capacity.

Additionally, the development involves 400 kV double-circuit transmission lines connecting Pirpainti with Jhanjharpur and Begusarai, and Begusarai with Bakhtiyarpur. The plan also includes 220 kV double-circuit lines linking Jhanjharpur with Bethauli and Begusarai with Begusarai Town. It incorporates a line-in-line-out arrangement for existing 220 kV and 132 kV transmission lines at Jhanjharpur, as well as the construction of 400 kV line bays at the Bakhtiyarpur GSS.

Kandarp Patel, Chief Executive Officer of Adani Energy Solutions, stated that the Pirpainti transmission scheme will establish a robust evacuation system for 2,400 MW of generation capacity while reinforcing the transmission backbone of Bihar. He added that the project will enhance grid reliability and resilience to support the state's growing power demand.

Upon completion, the project will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio. This expansion will bring the company’s total transmission network to 30,683 circuit kilometres and its transformation capacity to 146,585 MVA. With this latest contract win, AESL's transmission capital expenditure pipeline has grown to approximately ₹91,500 crore.

"Large-scale infrastructure projects secured through competitive bidding provide long-term revenue visibility and predictable cash flows for energy and transmission companies. By expanding its capital expenditure pipeline to roughly ₹91,500 crore, Adani Energy Solutions demonstrates a clear strategy to scale its operational footprint while directly supporting regional power grid reliability and meeting rising industrial and domestic energy demands." — Dr. Shishir Gupta, Founder & CEO, StartupLanes