BHP, the world's largest listed miner and top copper producer, announced on Monday that it plans to invest up to $17.4 billion to double its South Australian copper production by 2040. A final investment decision regarding the initiative is scheduled for the first half of next year.
According to the company, the investment path will raise annual copper output from the region to 650,000 metric tonnes. Geraldine Slattery, BHP's head of Australian operations, stated that the expansion can be funded entirely from existing copper cash flows, noting that Copper South Australia serves as a central pillar for future growth.
When accounting for byproducts such as uranium, silver, and gold, BHP expects the output from Copper South Australia to approach production levels comparable to Chile's Escondida, the world's largest copper mine. The regional growth supports BHP's broader roadmap to produce 2 million tonnes of copper annually from its global operations by the middle of the next decade. Slattery projects global copper demand to grow by 30 percent by 2040, reaching over 45 million tonnes per year, driven largely by electrification, digitalisation, and artificial intelligence demand.
BHP's copper division generated more value than its traditional iron ore mainstay for the first time in fiscal 2026. The latest expansion outlines how the company intends to develop the complex ore body, which contains high radioactivity and had previously been deferred due to high costs and commodity downturns.
The Copper South Australia operations comprise the Olympic Dam mine, the Carrapateena and Prominent Hill mines acquired from OZ Minerals in 2023, and the Ankata discovery. Financial analysts at UBS noted that historical operations in the region have faced challenges from operational instability, complex metallurgy, and infrastructure constraints related to water and power, resulting in low single-digit returns on capital employed until reaching 10 percent in fiscal 2026 amidst record-high commodity prices.
To counter these hurdles, BHP plans to implement block caving bulk mining and two-stage smelting to lower operating costs, targeting an internal rate of return between 14 percent and 17 percent. The expansion also involves doubling the capacity of its uranium processing plant to between 5,000 and 6,000 tonnes annually.
Water and power infrastructure remain critical variables for the project. BHP aims to offset its use of artesian water from the Great Artesian Basin by utilizing a planned 260-megalitre-a-day seawater desalination plant at Cape Hardy, which requires state and federal backing through the Northern Water infrastructure project. Additionally, the expansion necessitates electricity transmission upgrades, including a 275-kilovolt transmission line from Davenport.
"BHP's $17.4 billion capital allocation highlights a clear long-term strategy to capture surging global demand driven by electrification and digital infrastructure. While the technical complexities and infrastructure dependencies in South Australia present clear operational challenges, funding large-scale expansions from existing cash flows demonstrates disciplined capital management. For industry stakeholders, navigating regulatory approvals, water security, and power supply will be critical determinants of whether the project achieves its projected financial returns." — Dr. Shishir Gupta, Founder & CEO, StartupLanes