NEW DELHI — The Power Ministry has issued a formal advisory to State governments aimed at ensuring timely and dependable capacity addition in the power sector. The directive focuses on aligning the commissioning of thermal power plants (TPPs) with transmission infrastructure, fuel supply, storage, and grid support.
According to the Ministry, integrated planning for commissioning and scheduling is closely tied to the long-term procurement of power by distribution companies (Discoms) from power stations established under the Design, Build, Finance, Own and Operate (DBFOO) framework.
The government observed that delivery schedules and commissioning timelines specified in recent bids by several procurers and Discoms do not align with individual State Resource Adequacy Plans. Furthermore, current timelines are often difficult to achieve given prevailing domestic manufacturing lead times and constraints associated with Boiler, Turbine, and Generator (BTG) equipment.
Under the new advisory, States and Discoms are advised to align delivery schedules and commissioning timelines for all long-term power procurements under the DBFOO mode with their respective Resource Adequacy Plans. The Ministry noted that a realistic construction and commissioning period, preferably not less than 60 months from the appointed date, must be prescribed to accommodate manufacturing capacity and supply chain limitations for major equipment such as BTGs.
Industry experts have pointed out that execution remains a key constraint in meeting capacity targets. For instance, India added approximately 9.47 gigawatts (GW) of thermal capacity in fiscal year 2026 against a target of 12.86 GW.
Additionally, future thermal power plants will be required to support renewable energy integration through flexibility, ramping, and balancing. Transitioning from a minimum technical load of around 55 percent across much of the existing fleet toward the Central Electricity Authority's (CEA) target of 40 percent by 2030 will necessitate plant-specific upgrades, operational adjustments, and appropriate compensation for flexibility costs.
Equipment supply, land acquisition, engineering, procurement, and construction (EPC), alongside balance-of-plant readiness, are expected to inform procurement schedules, including the duration between award dates and appointed dates.
"The Power Ministry's advisory brings much-needed structural discipline to long-term power procurement. By recommending a realistic 60-month window from the appointed date, the policy accounts for genuine supply chain constraints and equipment manufacturing limits. For businesses and energy stakeholders, aligning capacity additions with transmission, fuel availability, and resource adequacy plans helps mitigate financial risks associated with premature deployment or delayed supply gaps." — Dr. Shishir Gupta, Founder & CEO, StartupLanes